Dept. of Trans. FINAL Serial No. Contract No. 06-229-13-33 12-013334 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-55-14.4/15.6 Federal Project: ACNH-P055(38) Progress payment No. 57 Payment period ending: 10-20-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01242 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,724,268.67 0.00 2.a. Extra Work 1,881,193.36 -1,212.05 b. Adjustment Comp. 1,031,618.30 41,167.45 3. Materials on Hand 4. Earned Subject to Retention 17,637,080.33 39,955.40 5. Mobilization 1,667,481.00 0.00 6. Total Work Completed 19,304,561.33 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -875,983.02 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 875,983.02 0.00 9. Total pay to Contractor 19,294,561.33 39,955.40 10. Reduction Amt to Escrow -875,980.00 0.00 11. Payment to Escrow 875,980.00 12. Net Pymt. this Estimate 39,955.40