Dept. of Trans. PROGRESS Serial No. Contract No. 00-332-13-59 12-035714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 12-ORA-5-41.5/43.5 Federal Project: ACIM-005-2(857) ACIM-005-2(857) ACNH-005-2(857) Progress payment No. 56 Payment period ending: 11-20-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00965 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,180,292.11 218,551.60 2.a. Extra Work 5,769,395.17 215,368.76 b. Adjustment Comp. 2,913,190.66 -231,467.36 3. Materials on Hand 25,041.00 -124,067.66 4. Earned Subject to Retention 53,887,918.94 78,385.34 5. Mobilization 5,131,394.00 0.00 6. Total Work Completed 58,994,271.94 7. Deductions -159,343.65 -19,400.48 8. a.Contract Retentions -2,694,395.95 -3,919.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 56,165,573.34 55,065.59 10. Reduction Amt to Escrow 11. Payment to Escrow 2,694,390.00 12. Net Pymt. this Estimate 55,065.59