Dept. of Trans. SEMI-FINAL Serial No. Contract No. 02-219-07-40 12-035714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-41.5/43.5 Federal Project: ACIM-005-2(857) ACIM-005-2(857) ACNH-005-2(857) Progress payment No. 65 Payment period ending: 09-29-00 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00965 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,234,726.55 300.00 2.a. Extra Work 6,037,052.93 0.00 b. Adjustment Comp. 5,380,634.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 56,652,414.19 300.00 5. Mobilization 5,131,394.00 0.00 6. Total Work Completed 61,783,808.19 7. Deductions -121,372.06 69,971.59 8. a.Contract Retentions -2,694,395.95 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,694,395.95 0.00 9. Total pay to Contractor 61,662,436.13 70,271.59 10. Reduction Amt to Escrow -2,694,390.00 0.00 11. Payment to Escrow 2,694,390.00 12. Net Pymt. this Estimate 70,271.59