Dept. of Trans. PROGRESS Serial No. Contract No. 02-171-07-29 12-035724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 12-ORA-5-41.5/43.5 Federal Project: NONE Progress payment No. 54 Payment period ending: 06-17-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01104 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,115,636.08 -198,775.09 2.a. Extra Work 4,945,964.96 249,976.20 b. Adjustment Comp. 1,840,917.13 0.00 3. Materials on Hand 2,745.50 -0.10 4. Earned Subject to Retention 57,905,263.67 51,201.01 5. Mobilization 5,024,829.00 0.00 6. Total Work Completed 62,927,347.17 7. Deductions -49,747.13 0.00 8. a.Contract Retentions -2,895,263.18 -2,560.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 59,985,082.36 48,640.96 10. Reduction Amt to Escrow 11. Payment to Escrow 2,895,260.00 12. Net Pymt. this Estimate 48,640.96