Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-018-09-32 12-035724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-5-41.5/43.5 Federal Project: NONE Progress payment No. 72 Payment period ending: 04-09-03 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01104 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,165,527.30 -247,496.00 2.a. Extra Work 6,816,298.79 68,096.96 b. Adjustment Comp. 2,502,190.97 243,699.85 3. Materials on Hand 4. Earned Subject to Retention 60,484,017.06 64,300.81 5. Mobilization 5,024,829.00 0.00 6. Total Work Completed 65,508,846.06 7. Deductions -18,205.10 32,287.44 8. a.Contract Retentions -2,943,265.66 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,943,265.66 0.00 9. Total pay to Contractor 65,490,640.96 96,588.25 10. Reduction Amt to Escrow -2,900,000.00 0.00 11. Payment to Escrow 2,900,000.00 12. Net Pymt. this Estimate 96,588.25