Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 03-125-08-53 12-040894 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 100% 12-ORA-22-R4.8/R5.7 Federal Project: ACNH-P022(20) Progress payment No. 15 Payment period ending: 04-20-03 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 01900 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,370,756.04 17,480.00 2.a. Extra Work 109,848.42 0.00 b. Adjustment Comp. 24,126.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,504,731.00 17,480.00 5. Mobilization 449,000.00 0.00 6. Total Work Completed 3,953,731.00 7. Deductions -103,650.40 0.00 8. a.Contract Retentions -175,236.55 -874.00 b. Unsatisfactory Prog. -874.00 -874.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,673,970.05 15,732.00 10. Reduction Amt to Escrow 11. Payment to Escrow 175,230.00 12. Net Pymt. this Estimate 15,732.00