Dept. of Trans. PROGRESS Serial No. Contract No. 08-148-10-46 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 36% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 18 Payment period ending: 05-20-08 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,206,029.98 905,894.60 2.a. Extra Work 376,491.66 5,513.95 b. Adjustment Comp. 93,400.00 0.00 3. Materials on Hand 0.00 -25,797.72 4. Earned Subject to Retention 11,675,921.64 885,610.83 5. Mobilization 2,850,000.00 0.00 6. Total Work Completed 14,525,921.64 7. Deductions -3,200.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,522,721.64 885,610.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 885,610.83