Dept. of Trans. PROGRESS Serial No. Contract No. 08-270-08-41 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 45% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 22 Payment period ending: 09-20-08 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,815,409.27 725,550.58 2.a. Extra Work 512,876.22 15,861.38 b. Adjustment Comp. 93,400.00 0.00 3. Materials on Hand 17,284.47 -8,513.25 4. Earned Subject to Retention 16,438,969.96 732,898.71 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 19,421,685.49 7. Deductions -7,866.67 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,431,103.29 732,898.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 732,898.71