Dept. of Trans. PROGRESS Serial No. Contract No. 09-056-09-02 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 56% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 27 Payment period ending: 02-20-09 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,410,904.20 614,864.29 2.a. Extra Work 565,410.26 6,686.85 b. Adjustment Comp. 120,613.42 27,213.42 3. Materials on Hand 16,130.62 -1,153.85 4. Earned Subject to Retention 20,113,058.50 647,610.71 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 23,096,927.88 7. Deductions -7,866.67 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,105,191.83 657,610.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 657,610.71