Dept. of Trans. PROGRESS Serial No. Contract No. 09-146-09-17 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 63% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 30 Payment period ending: 05-20-09 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,313,172.98 1,646,739.11 2.a. Extra Work 646,110.88 47,581.65 b. Adjustment Comp. 130,174.39 9,560.97 3. Materials on Hand 16,130.62 0.00 4. Earned Subject to Retention 24,105,588.87 1,703,881.73 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 27,089,458.25 7. Deductions -7,866.67 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,097,722.20 1,703,881.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,703,881.73