Dept. of Trans. PROGRESS Serial No. Contract No. 09-169-08-28 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 65% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 31 Payment period ending: 06-20-09 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,129,342.51 1,816,169.53 2.a. Extra Work 654,034.71 7,923.83 b. Adjustment Comp. 130,174.39 0.00 3. Materials on Hand 3,869.66 -12,260.96 4. Earned Subject to Retention 25,917,421.27 1,811,832.40 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 28,913,551.61 7. Deductions -7,866.67 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,909,554.60 1,811,832.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,811,832.40