Dept. of Trans. PROGRESS Serial No. Contract No. 09-208-13-55 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 68% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 32 Payment period ending: 07-20-09 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,910,840.28 781,497.77 2.a. Extra Work 658,350.63 4,315.92 b. Adjustment Comp. 83,411.59 -46,762.80 3. Materials on Hand 3,869.66 0.00 4. Earned Subject to Retention 26,656,472.16 739,050.89 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 29,652,602.50 7. Deductions -7,866.67 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,648,605.49 739,050.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 739,050.89