Dept. of Trans. PROGRESS Serial No. Contract No. 09-238-06-54 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 71% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 33 Payment period ending: 08-20-09 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,804,592.68 893,752.40 2.a. Extra Work 699,437.57 41,086.94 b. Adjustment Comp. 83,411.59 0.00 3. Materials on Hand 3,869.66 0.00 4. Earned Subject to Retention 27,591,311.50 934,839.34 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 30,587,441.84 7. Deductions -7,866.67 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,583,444.83 934,839.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 934,839.34