Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-08-19 12-056214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 73% 12-ORA-90-11.8/12.5 Federal Project: HP21-6212(11) L-6212(11) Progress payment No. 34 Payment period ending: 09-20-09 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 310189 FONTANA CA 92331-0189 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,105,422.98 300,830.30 2.a. Extra Work 705,388.56 5,950.99 b. Adjustment Comp. 83,411.59 0.00 3. Materials on Hand 0.00 -3,869.66 4. Earned Subject to Retention 27,894,223.13 302,911.63 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 30,894,223.13 7. Deductions -7,866.67 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,886,356.46 302,911.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 302,911.63