Dept. of Trans. PROGRESS Serial No. Contract No. 01-057-07-09 12-059234 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-35.8/36.9 Federal Project: ACIM-005-2(871) ACNH-005-2(871) DPU-071(4) Progress payment No. 40 Payment period ending: 02-20-01 FCI CONSTRUCTORS 12707 HIGH BLUFF DRIVE STE 13 SAN DIEGO CA 92130 Escrow No. 01099 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,436,619.38 108,282.70 2.a. Extra Work 1,980,272.93 82,047.48 b. Adjustment Comp. 2,033,257.67 156,443.46 3. Materials on Hand 49,739.28 49,739.28 4. Earned Subject to Retention 38,499,889.26 396,512.92 5. Mobilization 3,800,000.00 0.00 6. Total Work Completed 42,250,149.98 7. Deductions -30,000.00 -10,000.00 8. a.Contract Retentions -1,924,994.46 -19,825.64 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 40,344,894.80 366,687.28 10. Reduction Amt to Escrow 11. Payment to Escrow 1,924,990.00 12. Net Pymt. this Estimate 366,687.28