Dept. of Trans. PROGRESS Serial No. Contract No. 01-235-11-57 12-069514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 61% 12-ORA-405-7.6/9.6 Federal Project: NONE Progress payment No. 27 Payment period ending: 08-20-01 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 01380 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,943,939.36 956,277.65 2.a. Extra Work 326,161.26 2,952.94 b. Adjustment Comp. 134,502.68 0.00 3. Materials on Hand 239,307.27 -255,598.30 4. Earned Subject to Retention 19,643,910.57 703,632.29 5. Mobilization 3,075,000.00 0.00 6. Total Work Completed 22,479,603.30 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -982,195.53 -35,181.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,726,715.04 658,450.67 10. Reduction Amt to Escrow 11. Payment to Escrow 982,190.00 12. Net Pymt. this Estimate 658,450.67