Dept. of Trans. PROGRESS Serial No. Contract No. 01-268-15-01 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 17% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 09 Payment period ending: 09-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,679,238.97 1,370,361.96 2.a. Extra Work 316,868.75 276,070.04 b. Adjustment Comp. -71,028.26 -71,028.26 3. Materials on Hand 1,116,866.80 2,250.81 4. Earned Subject to Retention 8,041,946.26 1,577,654.55 5. Mobilization 3,944,993.25 0.00 6. Total Work Completed 10,870,072.71 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -804,194.63 -157,765.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,162,744.88 1,409,889.09 10. Reduction Amt to Escrow 11. Payment to Escrow 804,190.00 12. Net Pymt. this Estimate 1,409,889.09