Dept. of Trans. PROGRESS Serial No. Contract No. 01-295-10-20 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 23% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 10 Payment period ending: 10-19-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,178,071.80 1,498,832.83 2.a. Extra Work 361,752.92 44,884.17 b. Adjustment Comp. -71,028.26 0.00 3. Materials on Hand 1,041,382.65 -75,484.15 4. Earned Subject to Retention 9,510,179.11 1,468,232.85 5. Mobilization 3,944,993.25 0.00 6. Total Work Completed 12,413,789.71 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -951,017.91 -146,823.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,484,154.45 1,321,409.57 10. Reduction Amt to Escrow 11. Payment to Escrow 951,010.00 12. Net Pymt. this Estimate 1,321,409.57