Dept. of Trans. PROGRESS Serial No. Contract No. 01-325-09-50 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 26% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 11 Payment period ending: 11-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,394,233.62 1,216,161.82 2.a. Extra Work 373,557.06 11,804.14 b. Adjustment Comp. -41,844.27 29,183.99 3. Materials on Hand 1,027,353.23 -14,029.42 4. Earned Subject to Retention 10,753,299.64 1,243,120.53 5. Mobilization 4,996,991.45 1,051,998.20 6. Total Work Completed 14,722,937.86 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -959,652.15 -8,634.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,770,638.94 2,286,484.49 10. Reduction Amt to Escrow 11. Payment to Escrow 959,650.00 12. Net Pymt. this Estimate 2,286,484.49