Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 01-341-09-42 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 26% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 12 Payment period ending: 11-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,510,633.62 116,400.00 2.a. Extra Work 413,590.57 40,033.51 b. Adjustment Comp. -41,844.27 0.00 3. Materials on Hand 1,027,353.23 0.00 4. Earned Subject to Retention 10,909,733.15 156,433.51 5. Mobilization 4,996,991.45 0.00 6. Total Work Completed 14,879,371.37 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -959,652.15 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,927,072.45 156,433.51 10. Reduction Amt to Escrow 11. Payment to Escrow 959,650.00 12. Net Pymt. this Estimate 156,433.51