Dept. of Trans. PROGRESS Serial No. Contract No. 01-358-06-23 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 30% 28% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 13 Payment period ending: 12-20-01 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,652,724.44 1,142,090.82 2.a. Extra Work 526,591.50 113,000.93 b. Adjustment Comp. -31,844.27 10,000.00 3. Materials on Hand 1,460,066.97 432,713.74 4. Earned Subject to Retention 12,607,538.64 1,697,805.49 5. Mobilization 4,996,991.45 0.00 6. Total Work Completed 16,144,463.12 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -959,652.15 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,624,877.94 1,697,805.49 10. Reduction Amt to Escrow 11. Payment to Escrow 959,650.00 12. Net Pymt. this Estimate 1,697,805.49