Dept. of Trans. PROGRESS Serial No. Contract No. 02-295-08-52 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 25% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 24 Payment period ending: 10-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,008,829.24 929,120.72 2.a. Extra Work 1,725,861.07 95,334.41 b. Adjustment Comp. 202,869.91 -629.95 3. Materials on Hand 1,683,065.38 -12,518.71 4. Earned Subject to Retention 28,620,625.60 1,011,306.47 5. Mobilization 5,259,991.00 0.00 6. Total Work Completed 32,197,551.22 7. Deductions -40,000.00 -10,000.00 8. a.Contract Retentions -1,431,031.28 -50,565.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,409,585.32 950,741.15 10. Reduction Amt to Escrow 11. Payment to Escrow 1,431,030.00 12. Net Pymt. this Estimate 950,741.15