Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-117-07-07 12-0695U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-405-7.6/9.6 Federal Project: STP-5312(31) LN-5312(31) Progress payment No. 84 Payment period ending: 02-01-07 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01676 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,109,337.54 0.00 2.a. Extra Work 5,361,084.98 13,169.47 b. Adjustment Comp. 3,830,344.96 0.00 3. Materials on Hand 4. Earned Subject to Retention 57,300,767.48 13,169.47 5. Mobilization 5,259,991.00 0.00 6. Total Work Completed 62,560,758.48 7. Deductions 8. a.Contract Retentions -2,747,944.15 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,747,944.15 0.00 9. Total pay to Contractor 62,560,758.48 13,169.47 10. Reduction Amt to Escrow -2,747,940.00 0.00 11. Payment to Escrow 2,747,940.00 12. Net Pymt. this Estimate 13,169.47