Dept. of Trans. PROGRESS Serial No. Contract No. 13-113-08-17 12-071624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 66% 12-ORA-22-R0.7/R0.9 Federal Project: ARRA-X059(51) L-X059(51) CMLN-6212(13) Progress payment No. 32 Payment period ending: 04-20-13 ATKINSON CONTRACTORS L P 27422 PORTOLA PARKWAY STE 250 FOOTHILL RANCH CA 92610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,068,266.57 797,183.26 2.a. Extra Work 1,974,757.23 88,306.07 b. Adjustment Comp. 453,179.48 0.00 3. Materials on Hand 852,935.83 150,729.57 4. Earned Subject to Retention 38,349,139.11 1,036,218.90 5. Mobilization 5,900,000.00 0.00 6. Total Work Completed 43,396,203.28 7. Deductions -14,037.50 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,235,101.61 1,036,218.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,036,218.90