Dept. of Trans. PROGRESS Serial No. Contract No. 11-207-08-28 12-071634 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 12% 12-ORA-22-0.6/0.9 Federal Project: CMLN-6071(71) N-6071(71) Progress payment No. 07 Payment period ending: 07-20-11 ATKINSON CONTRACTORS L P 27422 PORTOLA PARKWAY STE 250 FOOTHILL RANCH CA 92610 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,258,573.70 1,689,308.04 2.a. Extra Work 127,155.72 27,975.63 b. Adjustment Comp. 3. Materials on Hand 945,841.72 -250,326.48 4. Earned Subject to Retention 6,331,571.14 1,466,957.19 5. Mobilization 4,725,000.00 0.00 6. Total Work Completed 10,110,729.42 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,051,571.14 1,461,957.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,461,957.19