Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-309-14-11 12-071634 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-22-0.6/0.9 CMLN-6071(71) N-6071(71) Progress payment No. 057 Payment period ending: 03-23-15 ATKINSON CONTRACTORS L P 18201 VON KARMAN AVE., STE800 IRVINE, CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 96,127,379.20 331,273.00 2. a. Extra Work 7,119,581.49 277,039.47 b. Adustment Comp. 6,635,853.72 51,059.84 3. Materials on Hand 4. Earned Subject to Retention 109,882,814.41 659,372.31 5. Mobilization 9,450,000.00 0.00 6. Total Work Completed 119,332,814.41 7. Deductions -407,465.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 118,925,349.41 659,372.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 659,372.31