Dept. of Trans. PROGRESS Serial No. Contract No. 16-299-11-37 12-0716U4 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 7% Location: Federal Project: 12-ORA-22-R0.3/R2.9 LM-6212(19) Progress payment No. 001 Payment period ending: 10-20-16 GRIFFITH COMPANY 4756 MISSION BLVD MONTCLAIR CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,395.00 26,395.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 26,395.00 26,395.00 5. Mobilization 6. Total Work Completed 26,395.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,395.00 26,395.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,395.00