Dept. of Trans. PROGRESS Serial No. Contract No. 17-055-08-52 12-0716U4 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 24% Location: Federal Project: 12-ORA-22-R0.3/R2.9 LM-6212(19) Progress payment No. 005 Payment period ending: 02-20-17 GRIFFITH COMPANY 4756 MISSION BLVD MONTCLAIR CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 261,809.53 5,847.00 2. a. Extra Work 54,487.64 8,760.91 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 316,297.17 14,607.91 5. Mobilization 131,250.00 0.00 6. Total Work Completed 447,547.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 447,547.17 14,607.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,607.91