Dept. of Trans. PROGRESS Serial No. Contract No. 17-173-15-45 12-0716U4 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 50% Location: Federal Project: 12-ORA-22-R0.3/R2.9 LM-6212(19) Progress payment No. 009 Payment period ending: 06-20-17 GRIFFITH COMPANY 4756 MISSION BLVD MONTCLAIR CA 91762 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 798,305.45 208,402.74 2. a. Extra Work 111,211.90 27,804.55 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 909,517.35 236,207.29 5. Mobilization 166,250.00 0.00 6. Total Work Completed 1,075,767.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,075,767.35 236,207.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 236,207.29