Dept. of Trans. PROGRESS Serial No. Contract No. 05-357-07-26 12-075304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-91-13.5/14.7 Federal Project: ACNH-P091(109) Progress payment No. 38 Payment period ending: 12-20-05 REYCO SMITH AND REYNOLDS EROSION CONTROL INC 206 N SMITH AVE CORONA CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,113,028.30 1,875.00 2.a. Extra Work 146,502.18 0.00 b. Adjustment Comp. -18,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,241,530.48 1,875.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 1,291,530.48 7. Deductions 8. a.Contract Retentions -62,076.52 -93.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,229,453.96 1,781.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,781.25