Dept. of Trans. PROGRESS Serial No. Contract No. 06-054-08-28 12-075304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-91-13.5/14.7 Federal Project: ACNH-P091(109) Progress payment No. 40 Payment period ending: 02-20-06 REYCO SMITH AND REYNOLDS EROSION CONTROL INC 206 N SMITH AVE CORONA CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,116,778.30 1,875.00 2.a. Extra Work 148,847.03 0.00 b. Adjustment Comp. -18,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,247,625.33 1,875.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 1,297,625.33 7. Deductions 8. a.Contract Retentions -62,381.27 -93.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,235,244.06 1,781.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,781.25