Dept. of Trans. PROGRESS Serial No. Contract No. 04-352-15-06 12-075404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-91-6.4/8.6 Federal Project: ACNH-P091(110) Progress payment No. 28 Payment period ending: 12-20-04 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02039 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,457,419.87 7,860.00 2.a. Extra Work 40,036.31 0.00 b. Adjustment Comp. 256,247.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,753,703.84 7,860.00 5. Mobilization 22,000.00 0.00 6. Total Work Completed 1,775,703.84 7. Deductions 8. a.Contract Retentions -87,685.19 -393.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,688,018.65 7,467.00 10. Reduction Amt to Escrow 11. Payment to Escrow 87,680.00 12. Net Pymt. this Estimate 7,467.00