Dept. of Trans. PROGRESS Serial No. Contract No. 03-052-09-11 12-075804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 31% 12-ORA-73-4.8/6.0 Federal Project: NONE Progress payment No. 07 Payment period ending: 02-20-03 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 324,063.98 61,157.55 2.a. Extra Work 117,663.75 1,663.75 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 441,727.73 62,821.30 5. Mobilization 66,000.00 0.00 6. Total Work Completed 507,727.73 7. Deductions -6,272.66 0.00 8. a.Contract Retentions -22,086.39 -3,141.07 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 479,368.68 59,680.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,680.23