Dept. of Trans. PROGRESS Serial No. Contract No. 07-331-11-31 12-078004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 25% 12-ORA-1-31.5/32.2 Federal Project: ACST-S001(536) P-S001(536) Progress payment No. 01 Payment period ending: 11-20-07 MC KENNA GENERAL ENGINEERING INC 1335 CORONA POINTE COURT CORONA CA 92879 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 168,502.04 168,502.04 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 168,502.04 168,502.04 5. Mobilization 11,250.00 11,250.00 6. Total Work Completed 179,752.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 179,752.04 179,752.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,752.04