Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-255-10-04 12-079204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-605-R0.0/R1.6 Federal Project: ACNH-605-2(899) I-605-2(899) ACNH-605-2(899) Progress payment No. 16 Payment period ending: 08-22-05 BANSHEE CONSTRUCTION COMPANY INC P. O. BOX 5247 SAN BERNARDINO, CA 92412 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,446,778.87 592,596.40 2.a. Extra Work 74,793.91 21,279.90 b. Adjustment Comp. 116,363.41 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,637,936.19 613,876.30 5. Mobilization 300,000.00 0.00 6. Total Work Completed 5,937,936.19 7. Deductions -1,062,857.51 -1,054,290.00 8. a.Contract Retentions -251,202.99 0.00 b. Unsatisfactory Prog. 0.00 31,099.94 c. Reduction after 95% Comp. 251,202.99 251,202.99 9. Total pay to Contractor 4,875,078.68 -158,110.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -158,110.77