Dept. of Trans. PROGRESS Serial No. Contract No. 02-053-07-40 12-083804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 24% 12-ORA-405-10.2/12.4 Federal Project: ACIM-405-2(890) ACIM-405-2(890) STPL-6212(8) Progress payment No. 13 Payment period ending: 02-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01677 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,544,083.28 865,079.13 2.a. Extra Work 387,302.45 48,639.12 b. Adjustment Comp. 50,294.87 3,688.30 3. Materials on Hand 27,489.41 5,758.02 4. Earned Subject to Retention 15,009,170.01 923,164.57 5. Mobilization 3,367,688.25 0.00 6. Total Work Completed 18,349,368.85 7. Deductions -40,000.00 -10,000.00 8. a.Contract Retentions -750,458.50 -46,158.23 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,586,399.76 867,006.34 10. Reduction Amt to Escrow 11. Payment to Escrow 750,450.00 12. Net Pymt. this Estimate 867,006.34