Dept. of Trans. PROGRESS Serial No. Contract No. 02-143-10-57 12-083804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 29% 12-ORA-405-10.2/12.4 Federal Project: ACIM-405-2(890) ACIM-405-2(890) STPL-6212(8) Progress payment No. 16 Payment period ending: 05-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01677 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,231,803.53 1,072,240.26 2.a. Extra Work 793,876.68 106,081.15 b. Adjustment Comp. 118,108.34 23,849.70 3. Materials on Hand 70,435.05 -47,652.71 4. Earned Subject to Retention 19,214,223.60 1,154,518.40 5. Mobilization 3,544,935.00 177,246.75 6. Total Work Completed 22,688,723.55 7. Deductions -40,000.00 0.00 8. a.Contract Retentions -960,711.18 -57,725.92 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,758,447.42 1,274,039.23 10. Reduction Amt to Escrow 11. Payment to Escrow 960,710.00 12. Net Pymt. this Estimate 1,274,039.23