Dept. of Trans. PROGRESS Serial No. Contract No. 02-269-13-31 12-083804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 37% 12-ORA-405-10.2/12.4 Federal Project: ACIM-405-2(890) ACIM-405-2(890) STPL-6212(8) Progress payment No. 20 Payment period ending: 09-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01677 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,893,742.89 1,155,593.51 2.a. Extra Work 875,751.03 26,125.53 b. Adjustment Comp. 544,237.31 166,102.11 3. Materials on Hand 129,512.18 -4,775.13 4. Earned Subject to Retention 24,443,243.41 1,343,046.02 5. Mobilization 3,544,935.00 0.00 6. Total Work Completed 27,858,666.23 7. Deductions -70,000.00 -10,000.00 8. a.Contract Retentions -1,222,162.17 -67,152.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,696,016.24 1,265,893.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,222,160.00 12. Net Pymt. this Estimate 1,265,893.72