Dept. of Trans. PROGRESS Serial No. Contract No. 02-297-08-12 12-083804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 39% 12-ORA-405-10.2/12.4 Federal Project: ACIM-405-2(890) ACIM-405-2(890) STPL-6212(8) Progress payment No. 21 Payment period ending: 10-20-02 M C M CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 01677 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,673,021.14 779,278.25 2.a. Extra Work 933,117.17 57,366.14 b. Adjustment Comp. 535,611.09 -8,626.22 3. Materials on Hand 102,253.03 -27,259.15 4. Earned Subject to Retention 25,244,002.43 800,759.02 5. Mobilization 3,544,935.00 0.00 6. Total Work Completed 28,686,684.40 7. Deductions -80,000.00 -10,000.00 8. a.Contract Retentions -1,262,200.12 -40,037.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,446,737.31 750,721.07 10. Reduction Amt to Escrow 11. Payment to Escrow 1,262,200.00 12. Net Pymt. this Estimate 750,721.07