Dept. of Trans. PROGRESS Serial No. Contract No. 04-111-15-33 12-097904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 70% 12-ORA-5-0.0/30.3 Federal Project: ACIM-005-2(906) G-005-2(906) Progress payment No. 08 Payment period ending: 04-20-04 ALCORN FENCE COMPANY P O BOX 1249 SUN VALLEY CA 91353 Escrow No. 02122 Total Estimate This Estimate 1. Contract Itms Without Mobil. 654,841.53 85,146.48 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 67,007.57 67,007.57 4. Earned Subject to Retention 721,849.10 152,154.05 5. Mobilization 66,749.85 0.00 6. Total Work Completed 721,591.38 7. Deductions 8. a.Contract Retentions -36,092.46 -4,462.01 b. Unsatisfactory Prog. -8,758.92 -7,607.70 c. Reduction after 95% Comp. 9. Total pay to Contractor 743,747.57 140,084.34 10. Reduction Amt to Escrow 11. Payment to Escrow 36,090.00 12. Net Pymt. this Estimate 140,084.34