Dept. of Trans. PROGRESS Serial No. Contract No. 04-057-08-34 12-099414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 80% 12-ORA-405-12.6/23.8 Federal Project: ACIM-405-2(907) ACIM-405-2(907) Progress payment No. 04 Payment period ending: 02-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 505,255.52 228,213.10 2.a. Extra Work 225.37 225.37 b. Adjustment Comp. 10,044.00 10,044.00 3. Materials on Hand 10,474.96 0.00 4. Earned Subject to Retention 525,999.85 238,482.47 5. Mobilization 65,000.00 3,250.00 6. Total Work Completed 580,524.89 7. Deductions 8. a.Contract Retentions -26,299.99 -11,924.12 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 564,699.86 229,808.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 229,808.35