Dept. of Trans. PROGRESS Serial No. Contract No. 04-169-11-17 12-099414 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-405-12.6/23.8 Federal Project: ACIM-405-2(907) ACIM-405-2(907) Progress payment No. 08 Payment period ending: 06-20-04 D W POWELL CONSTRUCTION INC P O BOX 1406 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 634,713.02 900.00 2.a. Extra Work 10,171.61 0.00 b. Adjustment Comp. 16,631.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 661,515.63 900.00 5. Mobilization 65,000.00 0.00 6. Total Work Completed 726,515.63 7. Deductions 8. a.Contract Retentions -33,075.78 -45.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 693,439.85 855.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 855.00