Dept. of Trans. PROGRESS Serial No. Contract No. 06-054-13-29 12-099424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 52% 12-ORA-405-16.5/17.8 Federal Project: ACIM-405-2(911) ACIM-405-2(911) Progress payment No. 03 Payment period ending: 02-20-06 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 552,296.23 64,999.80 2.a. Extra Work 42,230.17 42,230.17 b. Adjustment Comp. 3. Materials on Hand 12,323.40 0.00 4. Earned Subject to Retention 606,849.80 107,229.97 5. Mobilization 133,000.00 0.00 6. Total Work Completed 727,526.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 739,849.80 107,229.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,229.97