Dept. of Trans. PROGRESS Serial No. Contract No. 08-081-11-58 12-0A7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 39% 12-ORA-5-22.2/28.5 Federal Project: NONE Progress payment No. 06 Payment period ending: 03-20-08 DIVERSIFIED LANDSCAPE MANAGEMENT INC 12112 SEVERN WAY RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 399,301.65 159,199.52 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 399,301.65 159,199.52 5. Mobilization 28,500.00 6,000.00 6. Total Work Completed 427,801.65 7. Deductions 8. a.Contract Retentions -25,862.44 -1,852.23 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 401,939.21 163,347.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 163,347.29