Dept. of Trans. PROGRESS Serial No. Contract No. 11-326-14-42 12-0A7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 12-ORA-5-22.2/28.5 Federal Project: NONE Progress payment No. 50 Payment period ending: 11-20-11 DIVERSIFIED LANDSCAPE MANAGEMENT INC 23052-H ALICIA PARKWAY, #385 MISSION VIEJO CA 92692 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,238,377.01 11,466.00 2.a. Extra Work 25,366.77 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,263,743.78 11,466.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 1,293,743.78 7. Deductions 8. a.Contract Retentions -63,187.19 -573.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,230,556.59 10,892.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,892.70