Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-12-44 12-0C0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 21% 12-ORA-1-R0.2/R1.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-06 POWELL CONSTRUCTORS P O BOX 698 FONTANA CA 923340698 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 311,219.86 213,147.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 311,219.86 213,147.50 5. Mobilization 195,000.00 195,000.00 6. Total Work Completed 506,219.86 7. Deductions 8. a.Contract Retentions -31,121.99 -21,314.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 475,097.87 386,832.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 386,832.75