Dept. of Trans. PROGRESS Serial No. Contract No. 07-144-06-50 12-0C0704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 12-ORA-1-R0.2/R1.1 Federal Project: NONE Progress payment No. 09 Payment period ending: 05-20-07 POWELL CONSTRUCTORS 8555 BANANA AVE FONTANA CA 92335-3019 Escrow No. 02246 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,275,242.73 -10,350.00 2.a. Extra Work 58,674.57 24,414.88 b. Adjustment Comp. 133,146.08 3,436.95 3. Materials on Hand 4. Earned Subject to Retention 2,467,063.38 17,501.83 5. Mobilization 260,000.00 0.00 6. Total Work Completed 2,727,063.38 7. Deductions 8. a.Contract Retentions -123,353.17 -875.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,603,710.21 16,626.74 10. Reduction Amt to Escrow 11. Payment to Escrow 123,350.00 12. Net Pymt. this Estimate 16,626.74