Dept. of Trans. PROGRESS Serial No. Contract No. 22-263-08-47 12-0C1104 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 95% Location: Federal Project: 12-ORA-57-20.3/21.6 EPNH-P057(67) Progress payment No. 041 Payment period ending: 09-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,694,100.37 247,965.96 2. a. Extra Work 1,847,104.85 7,411.73 b. Adustment Comp. 171,064.40 0.00 3. Materials on Hand 255,874.33 -40,328.00 4. Earned Subject to Retention 43,968,143.95 215,049.69 5. Mobilization 3,603,699.00 0.00 6. Total Work Completed 47,315,968.62 7. Deductions -15,048.90 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,556,794.05 215,049.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 215,049.69