Dept. of Trans. PROGRESS Serial No. Contract No. 23-235-08-33 12-0C1104 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 90% Location: Federal Project: 12-ORA-57-20.3/21.6 EPNH-P057(67) Progress payment No. 049 Payment period ending: 08-20-23 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 43,013,021.41 25,461.53 2. a. Extra Work 2,137,345.36 185,271.60 b. Adustment Comp. 171,064.40 0.00 3. Materials on Hand 131,003.88 62,974.83 4. Earned Subject to Retention 45,452,435.05 273,707.96 5. Mobilization 3,603,699.00 0.00 6. Total Work Completed 48,925,130.17 7. Deductions -15,048.90 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,041,085.15 273,707.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 273,707.96