Dept. of Trans. SEMI-FINAL Serial No. Contract No. 04-338-13-49 12-0C2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 12-ORA-91-2.6/3.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-15-04 HIGHLAND CONSTRUCTION INC 133 NORTH PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 0.00 -28,495.00 2.a. Extra Work 125.53 125.53 b. Adjustment Comp. 156,286.81 156,286.81 3. Materials on Hand 4. Earned Subject to Retention 156,412.34 127,917.34 5. Mobilization 6. Total Work Completed 156,412.34 7. Deductions -7,820.61 -6,395.86 8. a.Contract Retentions -2,849.50 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,849.50 0.00 9. Total pay to Contractor 148,591.73 121,521.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 121,521.48